Facilities Planning and Design: Where Every Step Costs Money

Where to build and how to arrange it: site selection, layout types, systematic layout planning, flow analysis, layout algorithms, material handling, storage and manufacturing cells.

Facilities Planning and Design · 50 questions

Try 3 questions

1. In the factor-rating method for choosing a plant site, how is each candidate site compared?

  1. By the price of the land alone
  2. By its distance to the nearest capital city
  3. By a weighted sum of scores on key factors
Show the answer

Answer: By a weighted sum of scores on key factors

Planners pick factors such as labor, transport and utilities, weight them by importance and add up each site's weighted scores.

2. What is a key weakness of the factor-rating method for site selection?

  1. Weights and scores are subjective judgments
  2. It ignores all qualitative factors entirely
  3. It can only compare two sites at once
Show the answer

Answer: Weights and scores are subjective judgments

Different planners can assign different weights and scores, so the ranking may reflect opinions as much as facts.

3. In locational break-even analysis, a site with high fixed costs but low variable costs is best when?

  1. At high production volumes
  2. At low production volumes
  3. At any volume equally
Show the answer

Answer: At high production volumes

Low variable cost per unit only pays back the higher fixed cost once enough units are produced.