1. A surveyor measures 125.37 m but writes 152.37 m in the field book. What kind of error is this?
- A systematic error
- A blunder
- A random error
Show the answer
Answer: A blunder
Blunders are human mistakes such as transposed digits; they follow no pattern and must be caught by checks, not modeled statistically.
2. A tape is 3 mm too long. A line measured as 9 full tape lengths will read about how far off?
- 27 mm too short
- 9 mm too short
- 27 mm too long
Show the answer
Answer: 27 mm too short
A long tape covers more ground than it reports, so each length is under-read by 3 mm, and a systematic error adds up: 9 × 3 mm = 27 mm.
3. When many independent measurements with random errors are added together, how does the total random error grow?
- With the square root of their number
- In direct proportion to their number
- Not at all, since they cancel exactly
Show the answer
Answer: With the square root of their number
Random errors have random signs and partly cancel; their variances add, so the standard error of a sum of n equal parts is σ√n.
The rest of the quiz, a few questions at a time
BrainTok asks a few questions from quizzes like these before the apps you choose open, so your screen time turns into learning. For iPhone.
Join the betaMore Civil Engineering quizzes
- Construction Management: Construction project delivery methods · Design-Bid-Build
- Construction Management: Construction project delivery methods · Design-Build
- Environmental Engineering: Water quality parameters · Physical and Chemical Parameters
- Environmental Engineering: Why Sewage Plants Farm Bacteria
- Fluid Mechanics: Fluid properties · Density and Specific Gravity
- Fluid Mechanics: Why Golf Balls Have Dimples